Appearance
1.4d – Risk Management: Threats and Opportunities
Managing projects is fundamentally about managing uncertainty. Some uncertainty is a threat (things that could go wrong); some is an opportunity (things that could go better than expected).
1.4d.1 Identifying Risks
Threats (Negative Risks)
- Resource shortages (team sickness, turnover)
- Technical failures (platform instability)
- Schedule delays (vendor issues)
- External shifts (regulatory changes)
Opportunities (Positive Risks)
- Efficiency gains (new tool speeds up work)
- Technical breakthroughs
- Cost reductions (volume pricing)
- Early delivery potential
1.4d.2 Risk Analysis: Probability vs. Impact
Sarah learns to analyze risk using two dimensions:
- Probability: How likely is this to occur? (Low/Medium/High)
- Impact: How bad (or good) is the consequence? (Low/Medium/High)
Risk Score = Probability × Impact High-score risks are prioritized for proactive mitigation.
1.4d.3 Risk Response Strategies
For Threats
- Avoid: Change the plan to eliminate the risk (e.g., use a different technology).
- Mitigate: Reduce probability or impact (e.g., extra testing, backup servers).
- Transfer: Move the risk to a third party (e.g., insurance, fixed-price contracts).
- Accept: Acknowledge the risk and have a contingency plan if it happens.
For Opportunities
- Exploit: Ensure the opportunity happens (e.g., prioritize a high-value partnership).
- Enhance: Increase probability or impact (e.g., assign your best team to a breakthrough area).
- Share: Partner with others to capture the benefit.
- Accept: Take the benefit if it comes, but don't actively pursue it.
1.4d.4 The Risk Register
Sarah maintains a Risk Register, a living document tracking:
- Risk Description: What exactly might happen?
- Analysis: Current probability and impact score.
- Response Plan: What are we doing about it?
- Owner: Who is responsible for monitoring this risk?
- Status: Is the risk active, mitigated, or closed?
1.4d.5 Risk and Ways of Working
- Predictive: Extensive upfront identification and formal contingency planning.
- Agile: Continuous risk identification in every sprint. Mitigation through "spikes" (research tasks) and frequent feedback.
- Hybrid: Program-level risks managed predictively; team-level risks managed agilely.
1.4d.6 On the Exam: Risk Scenarios
Good Answers:
- Identify and assess the risk before acting.
- Choose a strategy that fits the risk's score.
- Assign clear owners.
- Monitor trends (are risks increasing or decreasing?).
Red Flags:
- Ignoring a risk and hoping for the best.
- Reacting only after a risk occurs (no plan).
- Treating all risks with the same level of urgency.
Key Concept
Risk management is not about eliminating risk (which is impossible); it's about being prepared so uncertainty doesn't derail your project.