Practice Exam 2: Agile & Hybrid Focus

Test your ability to lead in adaptive environments and handle complex interpersonal dynamics.

Practice Exam 2: Agility

Question 1 of 5
20%
A project has a Budget at Completion (BAC) of $400,000. Currently, EV = $180,000 and AC = $220,000. What is the CPI?
A. 0.82
B. 0.90
C. 1.10
D. 1.22