Knowledge Check: Monitoring & Closing
Test your mastery of performance metrics, change control, and the final handoff in the 2026 PMP context.
Chapter 9: Monitoring & Closing
Question 1 of 5
20%
A project reports a CPI of 0.95 and an SPI of 1.05. What is the status of the project?
EVM Cheatsheet
| Metric | Formula | Good Outcome |
|---|---|---|
| CPI (Cost Efficiency) | $EV / AC$ | $> 1.0$ |
| SPI (Schedule Efficiency) | $EV / PV$ | $> 1.0$ |
| CV (Cost Variance) | $EV - AC$ | Positive |
| SV (Schedule Variance) | $EV - PV$ | Positive |
📝 Exam Insight: If you see a question about a "claim" or "dispute" with a vendor, you CANNOT close the project until that claim is resolved (Procurement Closure). Detailed closure often involves legal or financial settlement.