Appearance
Formula Mastery & Project Glossary
Master the "Hard Science" of project management. This appendix covers every mathematical formula and technical definition required for the 2026 PMP Exam.
📊 Earned Value Management (EVM)
EVM is the most critical math section of the exam. If you master these 4 metrics, you can derive almost everything else.
The InputPV (Planned Value)
PV = % Planned × BAC
What you should have done by now according to the schedule.
The InputEV (Earned Value)
EV = % Actually Done × BAC
The budgeted value of the work actually completed.
The InputAC (Actual Cost)
AC = Total Spent
What you have actually paid to date.
EfficiencyCPI (Cost Index)
CPI = EV / AC
> 1.0 = Under Budget
< 1.0 = Over Budget
EfficiencySPI (Schedule Index)
SPI = EV / PV
> 1.0 = Ahead of Schedule
< 1.0 = Behind Schedule
ForecastingEAC (Projected Cost)
EAC = BAC / CPI
Predicts a final project cost if current efficiency continues.
📐 Estimation & Schedule Math
Beyond EVM, these formulas help you calculate certainty and communication complexity.
EstimationPERT (Three-Point)
(O + 4M + P) / 6
Weighs the "Most Likely" outcome 4x to account for uncertainty.
CommunicationChannels
N(N-1) / 2
Calculates the number of potential communication paths for N people.
ScheduleTotal Float
LS - ES or LF - EF
The amount of time a task can be delayed without delaying the project.
💰 Financial Selection Metrics
Used during Initiation (Chapter 5) to choose the right project.
| Metric | Rule of Thumb | Why? |
|---|---|---|
| NPV (Net Present Value) | Higher is Better | The total value in today's dollars. |
| IRR (Internal Rate of Return) | Higher is Better | The effective "interest rate" the project earns. |
| BCR (Benefit Cost Ratio) | > 1.0 is Good | For every $1 spent, you get >$1 back. |
| Payback Period | Shorter is Better | How fast you recover the initial investment. |
📖 Global Glossary (A-Z)
A - Adaptive to Artifact
- Adaptive: A project approach that is iterative or agile; responds to change.
- Artifact: Any document, template, or deliverable used to manage the project.
- Assumption: A factor held to be true for planning purposes without proof.
B - Backlog to Baseline
- Backlog: A prioritized list of work items (User Stories).
- Baseline: The approved version of a plan (Scope, Schedule, or Cost).
- Business Case: The economic justification for the project.
C - Change to Constraint
- Change Control: The process of reviewing and approving changes to baselines.
- Constraint: A limiting factor (Fixed deadline, budget cap).
- Critical Path: The longest sequence of tasks with zero float.
E - ESG to EVM
- ESG: Environmental, Social, and Governance criteria for sustainability.
- EVM: Earned Value Management; a method of measuring performance via math.
R - RACI to Risk
- RACI: Responsible, Accountable, Consulted, Informed matrix.
- Risk: An uncertain event that, if it occurs, has a positive or negative impact.
V - Value to Velocity
- Value: The net result of benefits minus costs.
- Velocity: The rate at which an agile team completes story points.